on 01-28-2014 12:29 PM
Hello Experts,
I would need your help to understand how do we close a service PO in srm.
I understand we can mark as delivery completed on the SES, and then check the final indicators on the PO.
For our client, the service PO doesn't have final delivery indicators, we have them suppressed for the PO.
The final indicators on the PO are checked.
The PO is appearing on the open PO report.
Any suggestions? How do I confirm if the PO is closed?
Regards,
Soumik
Hi Soumik,
For closed PO, it should have 'No further confirmation'(final_entry set as X) in all item levels.
Such POs will be considered as closed PO.
Best regards,
Ivy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.