We are in the process of upgrading the ECC6.0 to the EHP7. In the preprocessing steo main_shdcre/submod_shddbclone/dbclone it takes too long. The background jobs in SM37 was not intially stopped. So i was prompted to stop all the backgroubd jobs. I had run the program BTCTRNS1. After that when i check the Jobcs DBCLONE1,DBCLONE2, and DBCLONE3, it shows that DBCLONE1 job has been completed and the other Jobs  DBCLONE2 and DBCLONE3 are still in active mod. I have checked the logs DBCLONE1, DBCLONE2,and DBCLONE3, but no logs is updated.

Please advice.

Warm Regards,

Sudhakar G

Accepted Solutions (0)

Answers (3)

Answers (3)

deeraj_shetty
Participant
0 Kudos

Hi Sudhakar,

Please make sure DB performance is optimized before starting upgrade activity:

1. DB parameters tuning.

2. Latest MOPatch, Opatch and SAP Bundle patches applied.


Also increasing parallel processes numbers in the beginning of configuration phase will help in faster processing of these type of jobs.

Regards,

Deeraj Shetty

sunny_pahuja2
Active Contributor
0 Kudos

Hello,

DBCLONE phases usually takes lone time. It depends upon could of things like number of work process configured etc. Please refer to SAP note 1625638. Also, Please make sure that there are no dumps or memory related problem in the system.

Thanks,

Sunny

Reagan
Advisor
Advisor
0 Kudos

Hello

Connect to the main system and call Tx SM37 and do a "Check Status" for the jobs there.

Check whether they are getting changed.

Regards

RB