How overlapping of BOM level production (this is not overlapping of operations) can be achieved using CTM PPDS planning

Hello Experts,

We would like to achieve below scenario through CTM PPDS planning.

Scenario:- While completing production of entire quantity of one level bom
next level bom production should started.

At lower level BOM we need to produce 200 units, but before completing 200
units(suppose we have produce 100 units),
next upper level BOM production should get started.

Hence this is overlapping of BOM level production. This is not overlapping
of operations.

Do you know how this can be achieved in CTM PPDS planning.










200





BOM level"A"





200



BOM level"B"










Thanks for your help.

Best Regards

Abhimanyu

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 27, 2014 at 09:24 PM

    Hi Abhimanyu,

    In the overlapping scenario you describe, the restriction is related with the pegging (Pegging - SAP Library), a dynamic link between receipts and requirements, including orders of all BOM levels. This pegging is taken into account by the PP and DS strategy when you plan and schedule the orders.

    This pegging constrain can be ignored in the PP and DS strategy definition, but is not recommended because it prevents you to schedule an order when the required inputs are not available to execute it.

    A suitable solution for your scenario could be to define a lot size that force the orders to have a max size. In that way you will have more than one order to produce the same quantity. In the BOM level A, for example, you could use a max lot size of 100. Then you could schedule the order of the BOM level B after one order of the BOM level A, but before the total production is finished.

    100 100 BOM level A 100 100 BOM level B

    Hope it helps,

    Jorge

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member


      Hello Jorge/Kenneth/DB49/Sourabh,

      Thanks for your reply:)

      With PPDS PDS we can achieve our objective.

      But we also need same functionalities

      in CTM PPDS run

      following steps taken in PPDS PDS

      1. Activated business function SCM_APO_PPDS_PI to activate field in product master >>continuous IO pegging(we have checked this field)

      2. Maintained distribution key GLEI in Production version and BOM to get continuous input / output in PPDS PDS

      3. Executed PPDS optimizer with settings “consider exact continuous material flow”

      4. We got BOM level overlap output.

      *****Unfortunately we also need same functionalities in CTM PPDS run.******

      We have found some fields in PPDS PDS which are not available in CTM PDS. Eg...I/O

      scheduling>>Continuous with offset.

      We are still feeling that there should be something in CTM which will also help us to do similar plan using CTM PDS as we have in PPDS PDS planning.May be BAdi, or something else???

      Best Regards

      Abhimanyu

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.