how i can set the system MRP run exclude manual reservation.

Hi expert,

I have some problem, in case...

Planner : create independent requirement such as 10,140 ea in MD61.

and

Requester : create reservation as 10,140 ea in MB21 movement type 251.

after MRP run system create 2 planned order but actuality of 2 requirement(10,140) is a same requirement.

how i can set the system MRP run exclude this reservation.

thank you

1.jpg (46.3 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Posted on Jan 27, 2014 at 10:10 AM

    Hi Tanapong,

    You can use the MD_CHANGE_MRP_DATA BAdI to consider or to exclude special MRP elements other than the ones that are defined in the standard system. You can do this by using BAdi MD_CHANGE_MRP_DATA method CONSIDER_RESB. Please read the documentation of this BAdi also refer the modification from note 37697.

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 27, 2014 at 10:11 AM

    Hello

    The standard option would be to set a storage location excluded to MRP and direct these reservations to this storage location. You can do that on tab MRP4 of the material master.

    Another option is to use BAdI MD_CHANGE_MRP_DATA to set these reservations as non-relevant to MRP.

    BR

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 27, 2014 at 10:39 AM

    Hi,

    I have a little question, i see in OPJJ(availability check control, In/outward movements; mark for include reservation) and OMJJ(movement type, Update control/ WM movement types).

    how i can use this option.

    thank you

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Tanapong,

      OPJJ Availability check control is not relevant for MRP. OPJJ setting only useful for ATP check. MRP consider the setting of OPPI to consider the stock in MRP calculation. MRP has nothing to do with Availability check control OPJJ.

      Regards,

      R.Brahmankar

  • Posted on Jan 27, 2014 at 10:37 PM

    Why would they create two requirement requests (Independent req. + Manual reservation) for one actual requirement? The process itself doesn't seem right to me.

    I would suggest your manual material reservation person to un-check the check mark for "Movement Allowed" while creating Material reservation. This way only PIR gets netted during MRP calculations.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.