planned order to production order conversion check

Hi,

I want to put the check as without releasing the Document x; planned order should not be converted to production order. i want to get the error message as Document not released. please guide me.

Regards,

Mastan.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Jan 27, 2014 at 07:00 AM

    Hi Mastan,

    Check with action control indicator.

    Regards,

    Krishnendu.


    pastedImage_0.png (11.4 kB)
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 27, 2014 at 07:52 AM

    Hi Mastan,

    You need to develop something by using BAdI WORKORDER_UPDATE method AT_SAVE or AT_RELEASE


    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 27, 2014 at 10:05 AM

    Hi Mastan

    Use the user exit PPCO0007 function module EXIT_SAPLCOZV_001. This is exit while production order save, while saving you can use condition of Document release.

    Regards

    Kesava

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.