PR value is 130 , PO value is 85 - but budget exceeded

Dear All ,

The Service PR Value is 130 but PO was created for 85 only. But Budget is blocked for 130.

When I checked in CJ33 -- Availability Control Analysis. Its shows 130 only.

Any solution other than Technically Completing the activity, Because Service Entry Sheet is yet to be made.

Kindly help to rectify this problem.

Thanks in Advance.

Regards,

Shareeq

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Jan 26, 2014 at 12:25 PM

    Dear All,

    I think we will have to TECO the Activity. But still it allows SES

    Regards,

    Shareeq

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 27, 2014 at 05:40 AM

    Hi Shareeq,

    In service PR you might be used UOM AU. for UOM AU Value based commitment is active. Once the value based commitment is active system wont reduce the commitment only by creating the PO. If you want to reduce the PR commitment while creating PO then need to use quantity based commitment in the UOM customizing. In that case it is better not to use AU instead of that create a custom UOM where it can be used for services and value based commitment is not active.

    Thanks

    Abdul

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.