Dear all,

In the process of return sales with 651 movement, the cost of material return must be the same cost that came out, however when this process goes from one month to the other, where there was a change from the standard cost, this is not happened.

For example:

GD delivery sls.ord. 601 - Period 11/2013

Quantity 0.5 units

$ 117.67

Std price $ 235.34

Per unit price $ 227.63

GD returns unrestr. 651 - Period 12/2013

Quantity 0.5 units

$ 110.67

Std price $ 220.34

Per unit price $ 224.43

In this example the cost came out to $ 117.67 and returned $ 110.67 that can not happen.

Is there some setting that can be checked or process being reviewed?

Thanks