Hello,

When we are creating Sales Order due to low standard price maintained in material master, condition value for VPRS is 0.00. This results in Net Price as 0.00. Hence cost is not determined (shown in Incompletion log) and we are not able to save the sales orders.

Requirement: Make VPRS condition value as 0.01 when we have above scenario.

Question: Where can we make this change? Is there any user-exit where we can put up a logic to make VPRS condition value as 0.01?

In the attached image amount is 0.24 per 100 KG. This, for quantity of 1.998 KG results in condition value of 0.0047952 which is rounded to 0.00. This value we would like to make as 0.01.

Regards, Praveen

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jan 23, 2014 at 10:39 AM

    Hi,

    Create a pricing routine for calculating VPRS in VOFM. Assign the routine in the Pricing procedure configuration against condition type 'VPRS'. Coordinate with your SD functional consultant on this.

    Regards,

    DPM

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 23, 2014 at 11:08 AM

    Hi Praveen,

    Please check applied pricing procedure in V/08 and check with your functional if there is any routine on condition total. On condition total, condition value(XKWERT) comes ZERO if routine exists.

    Thanks

    Deependra

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 23, 2014 at 11:12 AM

    Hi

    Look for first a functional workaround. Please, see these notes

    SAP Note 1365939 - VPRS logic and Customizing settings in SD

    SAP Note 547570 - FAQ: VPRS in pricing

    SAP Note 201830 - Calculation of the net price of an item

    and check the value of this material in table MBEW (the valuation area can be the company or the plant).

    I hope this helps you

    Regards

    Eduardo

    pd: I am sorry, I forgot these two notes

    SAP Note 78799 - Rounding differences for condition VPRS

    SAP Note 80183 - Rounding

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.