Deal all SAP gurus,
I need your help! My company has a problem that we are trying to address when it comes to dual sourced parts. Here is some background info.
My company has 2 manufacturing sites and we've agreed upon a 60-40 split in productions requirements for Product A. They are plant 1 and I am plant 2.
Plant 1 loads the finishd good orders which drive down to the components. Problem is that the finished good component are built in both plant 1 and plant 2 to cover requirements.
I was thinking of setting up a quota arrangement with special procurement type X (In house production & External procurement). Once the order quantity is loaded they recieve a maximum of 40% of the orders and we recieve 60%. both plants use the same part number, how do we set up this part to correctly send the right signals of production to plant 1 and plant 2?
Can you help with this? Please let me know if you need further explanation
Thanks,
Ace
Hi Ace
The following note provides a very detailed explanation of the correct set up of a quota arrangement:
http://service.sap.com/sap/support/notes/1508647
You can find a link for this note and another issues related to the source determination on the following document:
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks but It is not allowsing me to click on the first link.
We've been running into problems in that Plant 1 loads the planned orders and Plant 2 (my plant) is the vendor.
How are parts correctly set up to do quota arrangement between a internally produced plant and a "vendor".
If someone could please provide specific steps and details in this thread to help get me started:
Thanks
ACE
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.