PR without material

jaheer_hussain
Active Contributor
0 Kudos

Hi,

I created one PR with item 00010 without material(I entered short text),Account assignment K.I entered  delivery date as 31.01.2014 and I also entered

Planned Delivery Time in Days as 10(Quantiites/dates tab),then my delivery date will be 10.02.2014 ???.But there will no changes in my delivery date(31.01.2014).There was no calculation .why it is so? Can somebody please advise me,please?

-Regards,

Accepted Solutions (1)

Accepted Solutions (1)

former_member183424
Active Contributor
0 Kudos

It will not calculate with delivery date.

PDT indicates "Number of calendar days needed to obtain the material or service if it

is procured externally."

You can see the PDT is carry forward from PR to PO

You can get more help about PDT by pressing F1 on PDT field.

If you use PDT in info record, then it will calculate with delivery date in PO.

**Message was edited by: Dëv Päträ

Answers (2)

Answers (2)

JL23
Active Contributor
0 Kudos

a manual entry has precedence over defaults.

do not enter a delivery date yourself, then SAP will calculate a delivery data based on the planned delivery time and PO creation date. so it will be  22.01. + 10 days.

if you want it a certain date, then enter this date and do not expect SAP to overwrite your entry

former_member183424
Active Contributor
0 Kudos

Exactly... This is happening for PO, but not for PR..

Former Member
0 Kudos

Hello Jaheer,

Not so sure what you mean to say but the planned delivery time influences delivery date in PR.

If you enter planned delivery time as 10 days it means 10 calendar days & system will propose delivery date after 10 days. If you are creating PR today then the proposed date should be 01.02.2014.

Are you entering the delivery date after entering the planned delivery days? In that case the date entered by you will over ride the proposed date by the system.