OPENPS 4.0 WORK is not download into MS Project 2010 from SAP PS

Former Member
0 Kudos

Dear Fellow,

I am using SAP Open Project System for Microsoft® Project Version: 4.04.02 and MS Project 2010 with ECC6 SAP GUI 730.

I am able to download and upload projects from MS project and SAP PS both sides.

There are some issues that I face during download and upload process which are:

     In SAP PS project I have maintained the work and duration for all activities

    

Download project attributes Project ID, WBS Elements, Network activities, Activity milestones into MS Project successfully.

Work is not downloaded into the MS Project?

How can I download work entered into SAP Project into MS Project work field.

Waiting for the Reply

Regards

Saqib Usman

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Fellows,

Refer to above post, I have checked if we maintain at least two things i.e.

1.     In SAP Open PS settings, check Object Types button check the checkbox for "Resource/Work center"

2. Work center must be entered in the internal activity.

 

Can any one let me know Is it possible to download work into MS project via openps with out maintaining of Work center into internal activity????

Waiting for reply

Regards

Saqib Usman

gocho14
Explorer
0 Kudos

This message was moderated.