on 01-20-2014 2:13 PM
Hi,
I would like t know is it possibl eo change the single cycle maint plan to multicycle? And how one can create a Maintenance Strategy? In IP 11 I am able to change the Packages of existing plan. But I want to create a new strategy.
Thanks in advance.
Sachin S. Kundap
Hi,
1. Create a maintenance strategy
2. Using the Strategy create a task list
3. Create maintenance plan using the defined strategy and assign the task list
4. Allign the scheduling as per single cycle plan due date
5. Set deletion to single cycle plan
Regards,
Raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It is not possible to change the cycle of plan once it is set ,try doing it by giving a user exit ,you could implement some logic through user exit
regards,
Muthukumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
1. plan type couldn't be changed.
2. you can create new strategy with IP11, select new entries.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sachin,
Once the plan is scheduled we cannot change the duration of cycle.
Regards,
Bhanu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.