on 01-20-2014 8:46 AM
Hi
I want to set the Preventive Maintenance Work Order Basic Dates interval to be determined from priority or to be manually entered somewhere in maintenance item. Is it possible and how?
At present to to provide interval between basic start and basic finish is calculated based on the task list operation duration.
How to enable the interval to be determined from prioriy or and any other way.
Thanks,
Panneer
Hello,
Please maintain through
Plant Maintenance and Customer Service =>Maintenance and Service Processing=>Maintenance and Service Orders=>General Data=>Define Priorities
Regards,
Joy Ghosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Panneer,
Also have a look at user-exit IWO10012 (Priority Handling on Central Header)
PeteA
Hi Panneer,
You can set priorities in the maintenance item. The difference between the start date and end date can be configured against the priorities using transaction type OIO2.
Regards,
Smart
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.