EK01-How does values are fetched

former_member185462
Active Participant
0 Kudos

Hi,

For the condition type VPRS ,the value is fetched from Accounting 1 view.

I have a doubt how & from where the value flows for EK01.

I have also gone through various liknks,but found it difficult to understand.

EK01 & EK02 Basics and Troubleshooting Guide - ERP SD - SCN Wiki

Pradeep

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

The value for EK01 condition type will be populated from Service order.This will be done when you maintain service entry sheet for your service order and when you create a sales order with reference to this service order.The value of the cost will be copied against EK01 condition type and will be appeared in the order.

Regards,

Krishna.

former_member186385
Active Contributor
0 Kudos


Hi Pradeep,

EK01 and EK02 are cost condition types populated from Project and service order

For example, if you have created a project from the Sales order (SD & PS Integration).. then the Planned cost of Project will be captured to sales order as EK02 and actual cost of the project will be captured to sales order as EK01 condition type

Similarly, service order Planned cost is captured as EK02 and Actual cost as EK01 condition type

these two condition types only populate for capturing actual and planned cost from order cost objects

regards,

santosh

Former Member
0 Kudos

Hi Mani,

EK01 is one of the standard cost condition type. It is used to provide the cost of materials manually in to the pricing. This is a manual condition type & is required when the cost materials needs to be provided manually in the order, instead of flowing from material master. The value will not flows automatically for this condition type.

Hope it's clear now.

Regards,

S.Himavanth.