on 01-15-2014 6:27 AM
Hi Experts,
Please giude.
Here i am creating STO today so as per plant delivery time (Days), system is determining the Delivery date but after ATP check run system is showing some other date
Ex. PO creation date = 15.01.2014
Planned del time = 2 Days
Delivery date = 19.01.2014 (Considering friday as holiday in Factory calender).
But for 19.01.2014 system is not committed the Quantity
and determine another date 21.01.2014 and comits the Quantity , i know this is the dat determine by ATP check and comits the Qty but how this date
will arrived i.e 21.01.2014?
Hi,
Could you please check MD04 for the material in supplying plant. You may check the available quantity for 19th as well as 21st. Please check and revert back.
Also, remove the planned delivery time in master data and check the scenario again.
Regards,
AKPT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.