STO delivery schedule

Former Member
0 Kudos


Hi Experts,

Please giude.

Here i am creating STO today so as per plant delivery time (Days), system is determining the Delivery date but after ATP check run system is showing some other date

Ex. PO creation date = 15.01.2014

     Planned del time = 2 Days

     Delivery date =  19.01.2014 (Considering friday as holiday in Factory calender).

    But for 19.01.2014 system is not committed the Quantity

    and determine another date 21.01.2014 and comits the Quantity , i know this is the dat determine by ATP check and comits the Qty but how this date

    will arrived i.e 21.01.2014?

Accepted Solutions (0)

Answers (1)

Answers (1)

Prasoon
Active Contributor
0 Kudos

Hi,

   Could you please check MD04 for the material in supplying plant. You may check the available quantity for 19th as well as 21st. Please check and revert back.

    Also, remove the planned delivery time in master data and check the scenario again.

Regards,

AKPT