Delivery from project and PGI doesn't result in goods movement.

Dear All,

We have been testing non valuated project stock scenario for the client, i tested the complete scenario in sandbox (material planning to PGI) and it worked perfectly fine . But in development client when i go for PGI (taking reference of delivery document created thru CNS0) transaction processed but without any goods movement , i checked the document flow and found that in place of goods issue document system is creating picking request and confirmation of services and when i checked delivery document i found movement type field is blank.

Please suggest.

Thanks.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jan 13, 2014 at 07:44 AM

    Hello Akhil,

    If results are working fine in Sandbox system,then compare configurations in Development System with Sandbox system. ( For e.g Item Categories, Item Category Determination, Copy Control for Deliveries)

    You can take help of SD consultant as well for this.

    Regards

    Tushar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.