Hi

We have three level BOM structure of finished goods. 1st level Semi Finished is produced and issued to be used in 2nd level Semi Finished goods. 2nd level Semi Finished good is used in a Finished good finally (i.e. 3rd level).

Finished Good

- Packing material # 1

- Packing material # 2

- O Head

- 2nd level Semi Finished Good

- Raw Material # 1

- Labor Actvity

- 1st level Semi Finished Good

- Raw Material # 2

- Labor activity

We use process orders, product cost by order and settle process order at month end. We use distribution cycles, KKS2, KSII, revaluation of process orders, variance calculation KKS1, and settlement CO88.

We need a single multi level variance analysis report showing material #, material name, external material group, actual quantities, standard quantities, actual costs, standard costs, variance, variance categories, etc.

The report should have both the SFG/FG being produced and its components. The selection screen should have selection for material preferably or process order list and run for a period.

So we can analyze multi level variance analysis at a glance and can export to MS Excel. Is there any standard report or can we generate using some configuration or report painter?

Please help

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Posted on Jan 10, 2014 at 04:41 PM

    Hi

    For actual variance analysis, if you enter FG material code, it will give variance analysis only for FG material. it won't show for SFG in that case. If you want to see for sfg, then you Ned to enter sfg code in input screen

    You can use reports like KKBC_HOE or KKO0

    Ajay M

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2014 at 10:31 PM

    Hi..

    Our business have also request this requirement continuously.

    I checked whether SAP have this report which you mentioned above but I cannot find this report.

    So, I plan to develop z-program through ABAPER but I don’t know how to design the logic.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 11, 2014 at 03:45 AM

    Dear Chris

    For all the levels variance analysis is I think not available in Standard reporting. For one material type you can do as Ajay Sir said. You need to have a friendship with ABAP guy😉 or you can try report painter.

    Regards

    Rajneesh Saxena

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.