Hello all,

I have the following situation. I have created a change request and change document in our Solution Manager system.

I also made transport request TSTKxxxxxx. I made some changes in our development system (Badi Implementation), but after that

I discovered that it does not solve the problem. I did not put the transport in the QUA or PRD systems.

Now I have change document and transport, with changes that I don't want.

What is the best practice to cancel all that?

I think deleting the transport request is not a good option. Perhaps I should REVERT all changes

and just execute the do/undo transport in the other systems?

Regards

ILIAN

Accepted Solutions (0)

Answers (2)

Answers (2)

JPReyes
Active Contributor
0 Kudos

Hi Ilian,

The best approach is to create a new transport with the corrections to the first transport and then transport both all the way to production.

This is the best for traceability and complies with change management.

Regards, Juan

AtulKumarJain
Active Contributor
0 Kudos

Hi ILian,

You answer your question by yourself


I think deleting the transport request is not a good option. Perhaps I should REVERT all changes

and just execute the do/undo transport in the other systems

Yes doing the do/undo is the best method to do it.

BR