I wander how to patch a BI7.3 based netweaver 7.3 system. It contains an ABAP and an Java system. If I start SUM I have to use na <sid>adm user. Due to the fact I have two systems I have two users.

Does this means I have to run SUM twice(once for Java and once for ABAP)?

Thank you in advance

Jan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Yes, you will have to patch AS ABAP and AS JAVA separately. Only in case of a dual stack system are both stacks patched simultaneously.

Answers (1)

Answers (1)

Reagan
Advisor
Advisor
0 Kudos

You need to start SUM twice. One for JAVA and one for ABAP. Had this been a dual stack system (which is not supported anymore) SUM needs to be started only once and it will detect the ABAP and the Java stacks and will provide two separate tabs in the upgrade console.