on 01-09-2014 4:57 AM
Hi All,
I have a requirement where :-
Retrieve all the open, completed/confirmed, aborted and cancelled Work Orders at different date ranges (-n/+n days from today) for different levels of asset as shown below
Asset Level | Going Back (-n) | Going Forward (+n) |
Site | -1 | +1 |
Process Group | -7 | +7 |
Plant Group | -7 | +7 |
Plant System | -30 | +30 |
Plant Item (Equipment) | -30 | +30 |
How should i configure this requirement for different levels of asset?
Can anyone please help me out.
Thanks and Regards,
Akshay Subbaraj
Hi Akshay ,
The above requirement can be met using IW39 report assuming dates as basic start date . Also in std SAP there is no such status cancelled PM order etc. For this you can create user status at order header level .
For different levels of equipment you can just mention functional location of equipments or equipment no . Just check you business requirement suitability . If possible external no. range for equipments can also be used .
REgards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Akshay Subbaraj
Create some IW39/IW49N variant for each of the requirements above.
In the variant you can set dynamic dates.
You can also use TVARV settings for your dates
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.