Skip to Content
author's profile photo Former Member
Former Member

report for Splitting Overhead between Fixed and Variable?

We need a way to get to contribution margin. This is splitting out the Overhead between variable and fixed. We tried to do
it manually last year and could not tie to the total numbers. We are using % based overhead for our overhead calculation and in our costing sheet we have maintained Base,Overhead rate and Credit .We have plant specific costing sheets

We dont have COPA implemanted

Base=Labour/OH Cost Elements

OH=% maintained

Credit=One cost center per plant for everything

Any suggestions please?

Thanks

Fransisco

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Jan 09, 2014 at 12:31 AM

    Hi

    Check the recently contributed doc by Jose

    You can see it in the 1st page of controlling forum once you are in it under section top liked content

    Ajay M

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 09, 2014 at 05:19 AM

    Dear fransisco

    Below is the link what Ajay sir is mentioned. A very good and helpful link indeed.

    http://scn.sap.com/docs/DOC-50323

    Regards

    Rajneesh Saxena

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.