Cancelled network activity confirmation but actual hours still capture

Dear all,

I have executed CN29 to cancel confirmation on the network activity and the status of the network activity is now REL, however there is 22.1 H still capture as actual and also there is forecast hours.

Could you please advise on this? How to remove the actual hours?

Thanks and regards,

Jessie

1.png (27.8 kB)
Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Posted on Jan 08, 2014 at 01:49 PM

    Hi Jessie,

    does the activiy have any activity-elements? Otherwise it looks like inconsistent.

    Kind regards,

    Zhenbo

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 10, 2014 at 06:00 AM

    Hi Jess,

    First of all please check already booked approved hours details in CJI3 report like where they are booked and then try to cancel the approve hours.

    Please find the below link : -

    http://wiki.scn.sap.com/wiki/display/ERPHCM/Cancelation+of+Time+Sheet+Data

    http://scn.sap.com/thread/1112145

    Regards

    Shashank

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.