MRP Message Horizon/Time Range

Former Member
0 Kudos


Hello Experts,

MRP Messages e.g. "10"  for Schedule in do have a setting when it occures e.g.  Re-scheduled date "X Days " days before Scheduled (MRP) Date.

Where in customizing can I find this setting & is it adjustable ?

Thanks in advance

Jörg

Accepted Solutions (1)

Accepted Solutions (1)

former_member209265
Active Contributor
0 Kudos

Hi Jorg,

Check these two setting in customizing. All the messages you can not change. You can create a new one.

Hope this helps.

Regards,

Krishnendu

Former Member
0 Kudos

Hello Krishnendu,

Thanks for for reply,

in this section I see the Details like Key, Execptn. message, Priority, Selection group ..... .

I do not see the value e.g. day which triggers the occurence of this message e.g. 1 or more days between sched. date and re-sched. date for message 10 sched. in.

Regards

Jörg


Former Member
0 Kudos

Jörg,

These settings are done in Rescheduling Configuration.  OMDW

Best Regards,

DB49