View Cost Center By Material Number

Hello Everyone,

Are any of you aware of an SAP Transaction where I can input multiple material numbers at once to generate a report displaying specific cost centers assigned to each material number?

For example, if material number 123456 has cost centers 2081110 & 2081210 assigned, the report would display this information in a column. Any suggestions will be greatly appreciated.

Thanks for your time.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Best Answer
    Posted on Jan 07, 2014 at 07:38 PM

    John,

    Interesting requirement

    I hope you are talking about consumption data, as there is no where you assign cost center to Material in SAP.There is no direct link of material master to cost center. However Routing are assigned to material and then From Routing several work centers and then cost centers.

    Yes consumption data is linked in some cases to cost center but not material master (master data).

    Now coming back to your report may be you can query it from table like MARC, CRCO, PLKO alongwith MSEG or may be an ABAP report to help you get there

    Let me know if you succeed with it

    Thanks

    Hrusikesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 07, 2014 at 07:16 PM

    Hi Jonh,

    There are no report as you describe in SAP controlling.

    However you can analyse the Specification Reports from materials.

    Try to use the following Reports:

    For Standard Cost: CK84_99

    For Actual Cost: CKMLQS

    BR,

    RK

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 07, 2014 at 07:49 PM

    Thank you for your comments gentlemen. I guess to be more specific with the purpose of this request, I am putting together a report and in this report seek to reference the cost centers involved with each material number listed line by line. I was originally going to use CK11N to gather this
    data however this is time consuming and must be done one at a time.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.