Hi Gurus,

When I'm generating absence quota I'm being encountered by this error

I've changes IT 0003 and PA03 but still getting same error please help me out from it is coming

Yours

Mohan

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member193210
Active Contributor
0 Kudos

The error message indicates that it is related to the generation of a Quota, and specifies that "Changes in retroactive accounting for time evaluation not possible".

If you execute Time Evaluation in test mode, with the "Display Log" box checked, you'll be able to double-click on function QUOTA to see it's Input and Processing.  With that information, try to identify what Quota is not compatible with the employee's WPBP (or EsgGr/PsaGr) on the day that the error happens.

You may have tried to limit retroactive Time Evaluation, but something causes the system to go retroactively (you never mentioned on what date the error happens), and something is not compatible with the configuration on the date the error happens.

leelamohan_kavali
Active Contributor
0 Kudos

Hi Rémi Corriveau,

According to you i did check Quota function kindly find below result

Log Tree:

PU03

Here I would like to generate quota from 01.11.2013 to 31.12.2013 but here system is taking his hiring date kindly let me know from where it's taking even i did check control record maintained 01.11.2013.

Yours

Mohan

former_member193210
Active Contributor
0 Kudos

As of what date is the system doing the Time Evaluation?  Is it 15.10.2013 ?

Was the employee initially hired on 15.10.2013 and hiring date was changed ?

Does the employee have some Infotypes that are valid as of 15.10.2013 ?

leelamohan_kavali
Active Contributor
0 Kudos

Hi Rémi Corriveau,

15.10.2013 is hiring date.

Regards

Mohan

former_member193210
Active Contributor
0 Kudos

If that is also the date the Time Evaluation error happens, then check the employee's Master Data for that day and double check the relevant Esg and Psa Groupings, specially for Quotas.

Try to find out why the system can't create Quota 91 (Rule 225) or Quota 92 (Rule 776) for that employee.

sikindar_a
Active Contributor
0 Kudos

Dont not change T569R , that effects for other employees too Check the earliest date in PU03 and control record as suggested by other expert that should solve the issue

Former Member
0 Kudos

Thanks Sikinder for the suggestion, I completely missed that.

leelamohan_kavali
Active Contributor
0 Kudos

Hi Upendra,

Kindly let me know how it's behaving according to you I've changed PU03 now quota is generating but showing one error with out displaying.

Kindly pull me out from this error pls..................

Yours

Mohan

Former Member
0 Kudos

There will be an error message expand all respective nodes and see what is the error.

Former Member
0 Kudos

Please mention the dates you are running this for and share screen shot of 0003.

BR

Upen

leelamohan_kavali
Active Contributor
0 Kudos

Hi Upendra,

Kindly find below screen

IT 0003

PA03

Yours

Mohan

Former Member
0 Kudos

Mohan,

I needed the dates you are running PT60 for and I believe that you are trying to run time eval before 01.11.2013 which is mentioned in Earl.Pers.Rec. Date under time eval tab. So try to restrict the system from going beyond the said date.

BR

Upendra

leelamohan_kavali
Active Contributor
0 Kudos

Hi Upendra,

PT60

Yours

Mohan

Former Member
0 Kudos

Okey Remove the date in Earl.Pers.Rec. Date and try to run the PT60 in simulation

leelamohan_kavali
Active Contributor
0 Kudos

Hi Upendra,

Getting same error

Please help me out

Yours

Mohan

Former Member
0 Kudos

1. Check if the error is employee specific

2. check the dates in V_T569R table

3. Also check the quota dates

former_member193652
Active Contributor
0 Kudos

Hi Mohan,

In which day of time evaluation have this problem? Tray to find what is quota generation date? Doble click on QUOTA function in output log. maybe quota valid date is for a year and it has overlap with retroactive dates.

Regards,

Omid