I'm trying to carry out a HR cost transfer using KPHR, but i'm getting the error that " No plan scenario found".


i'm unable to find where is this plan scenario to be created, even checked with HR guys but they too hav'nt found the same.


Please help.


Regards,

Charmaine

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Jan 06, 2014 at 12:40 AM

    You create a planning scenario with Transaction MS31

    or by following the menu path Logistics • Production • Production Planning • Long-Term Planning • Scenario • Create.

    Add a comment
    10|10000 characters needed characters exceeded

    • SK D Charmaine Martin

      Check SPRO - Personnel management - Personnel cost planning and simulation - Planning preparation - Create planning scenario.

      I think this planning scenario needs to be assigned to be assigned somewhere which I am not fully aware off but I hope it should be in the same node.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.