Operation releasing

Hi,

I have a task list with a number of maintenance operations. I would like to insert some relationship or trigger between the operations to control when each one is released, e.g that operation 2 is not released until operation 1 is complete and so on.

Currently all operations are released at the same time. I have tried using 'network graphic' in T-code IA06 by inserting FS (finish-start) links betwwen operations but this doesn't seem to make any difference.

Any help would be much appreciated.

Thanks,

Dominick

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 03, 2014 at 09:41 AM

    Thanks for your replies.

    What do you mean by user status?

    Also what is the point of relationships if they do not control the release of operations?

    Thanks,

    Dominick

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Relationships schedules the order operations accordingly with the scheduled date & time. This will not control the business transactions such as confirmation of operations, goods movement etc.,

      The link which you provided will be useful with Production Order. I feel, its not available with PM Order.

      To know more about User status:

      http://scn.sap.com/docs/DOC-33909

  • author's profile photo Former Member
    Former Member
    Posted on Jan 03, 2014 at 08:54 AM

    You can use User status control for operations to release one by one.

    If you want to restrict for any user, then user status & development can be done.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jan 03, 2014 at 08:59 AM

    Hi,

    when you release order header all operation would be released, you can not release in operation level with system status.

    However, you can set user status for release each operation.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 03, 2014 at 10:05 AM

    This seems to be what i am looking for but im not sure how i would implement it

    Creating a Trigger Point - Routings (PP-BD-RTG) - SAP Library

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.