Former Member
0 Kudos


When I make some changes in order like assigning the PRT equipment to an operation it disappears from the Planning board /MRSS/PLBOGEN

Also the Notification is not showing up on the other side the Order is created on behalf of Notification.

Please give some help.

Accepted Solutions (1)

Accepted Solutions (1)

former_member201296
Contributor
0 Kudos

Please check the Work center associated with that particular operation. Check if you have mentioned the Other formula as SAP 008 & Distribution formula SAP 000 (generally) on Capacity Tab in the work center & on scheduling Tab the other formula should be the SAP 004.

Also check the HR assignments you have taken for the Person in HRMS assignments

On the other side you also check if you facing the problem while taking PRT tool as Resource

Check all the PRT Related fields are updated like task list usage, load & control key etc.

Former Member
0 Kudos

Manage to sort it out I have made chanes in the workcentre didn't work out finally deletd the workcentre & assigned new it worked but could not understand what was the problem.

Thank you.