on 01-02-2014 12:57 PM
Hi All,
I am trying to track change document for any change done in settlement rule (such as changing settlement receiver)
of maintenance order but could not get .I am opening the settlement rule page following path Go to-change document
but could not find who has changed the settlement receiver.
Please suggest.
rgds
Hi,
Please refer to following SAP Note 499701 - Change documents for settlement rules.
Regards,
Grzegorz
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Thanks a lot for the valuable information. Before I close this ,can you please suggest my below doubt.
By mistake actual cost of maintenance order is settled to a wrong cost center . This cost center is maintained wrongly as settlement receiver in maintenance order.But actually the cost is supposed to be settled in a WBS element .Also,year end closing is done. How can I now transfer this cost to the WBS element? What are the impacts if we keep as it is in case we can not transfer the cost to WBS element?
Please suggest .
Hi Pranjal,
You can reverse settlement which is already done in Tcode KO88 and again settle to a WBS element
For more information please go through thread http://scn.sap.com/thread/526944
Regarding Financial impact better discuss with FI / CO consultant or post your query in Controlling Forum.
Regards,
sitanshu