Dear expert I perform a result analysis settlement, but as the WBS in status release I did not expect any posting to the project itself (meaning no CO document) but only to the FI. I use (03) Cost-Based POC Method .It was the first period and I have only cost been posted to the wbs (I have also plan cost and plan revenue) Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi  Dan,

Yes, Your query is not clear.. Do you want  there should not be any CO postings in the 1st period ?

Please clarify ?

Regards,

M.Amarendra

Former Member
0 Kudos

HI Dan,

What is your query? I did not understood your question?

Thanks and regards,