Orders created for 2 different dates from 1 maintenance plan

Former Member
0 Kudos

Dear Expert,

I created Maintenance plans with 2 maintenance item. when i scheduled it 2 work order created but the basic date of both the work orders having different date. what could be the reason ?

thanks

Kamlesh

Accepted Solutions (1)

Accepted Solutions (1)

peter_atkin
Active Contributor
0 Kudos

Kamlesh

Check the capacity/scheduling data on the various main and operation work centres via transaction IR03.

Also check the change log to ensure the dates haven't been manually changed via IW33.

PeteA

Answers (3)

Answers (3)

Former Member
0 Kudos

it is helpful if you send the screen shots of maintenance items and orders.

linganna

former_member209020
Active Participant
0 Kudos

This message was moderated.

peter_atkin
Active Contributor
0 Kudos

Some questions:

  • Are the orders in the same plant
  • Do the orders have the same same work centres
  • Are the order types the same

PeteA

Former Member
0 Kudos

Dear Peter,

  • Are the orders in the same plant

                     Yes

  • Do the orders have the same same work centres

                    No , different work centre

  • Are the order types the same

                    Yes

Except Equipment and Work centre everything is same.

regard

Kamlesh

former_member196951
Active Participant
0 Kudos

have you got the cause & solution ?

if yes, please share the reasons behind it; if no, share the snapshots of maint. items & orders.

Former Member
0 Kudos

What is the priority maintained in both Maintenance Items?? Based on that only, Basic start date will be updated.