Operation Level Teco

we are doing teco Header level but my client Want Operation level It's Possible, If Possible In The sense help me

EX:10-Operation

20-Operation

30-Operation(3'rd Operation Technically Problem, But I can continue in next Operation So I want Do Teco for 3"rd Operation)

40-Operation

50-Operation

I'm Waiting for Replay,,,,,,,

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jan 06, 2014 at 04:01 AM


    Hi Thiya

    PM orders maintain status at the header level so is the TECO can be done at header.

    I havent personally seen any status at operation level which means its not possible to TECO individual operations. if you dont get reply from the forum, may be best is to contact SAP via OSS.

    If you find positive answer, please share it here

    Regards

    Sana

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.