The date 3,112 is not convertible (Please Correct)

SaniketK
Participant
0 Kudos

Hi Gurus,

When creating process order we are facing error "The date 3,112 is not convertible (Please Correct)"

Please suggest on same its very urgent.

Regards,

Saniket

Accepted Solutions (1)

Accepted Solutions (1)

former_member207022
Active Contributor
0 Kudos

Hi,

It is due to inconsisitency  on a date, which usually means a date outside of the factory calendar validity.

Check the factory calendar in transaction SCAL, whether the production order given date is working day. Extend the factory calendar period.

If the issue happens when you are trying to convert the planned order to production order, check if there isn't any date on the planned or either in the work center that is outside the factory calendar validity.

Regards

Ganesh M

Answers (8)

Answers (8)

SaniketK
Participant
0 Kudos

Dear All,

Thank you very much for your replies. The error was of Factory calender only. 1st i was extended it only for 2014 still the error not resolves. But when i extend it for 2015, the error get resolved. The term 3,112 is the working days as per mentioned by Mr. Amit and as per Ganesh said order date goes outside of the factory calendar validity.


WISH YOU VERY HAPPY NEW YEAR 2014.

Regards,

Saniket

Former Member
0 Kudos

Hello Saniket,

As per the analysis using function modules FACTORYDATE_CONVERT_TO_DATE and RKE_SELECT_FACTDAYS_FOR_PERIOD,  3112 are the working days in factory calender which you maintain. So that it gives the error in process order.

Please maintain factory calender and then check.

Regards,

Amit Deokar

former_member209265
Active Contributor
0 Kudos

Hi,

Please check the user setting for date format.

Success.

Krish.

SaniketK
Participant
0 Kudos

Hi Krish,

Date format is DD.MM.YY

Regards,

Saniket

former_member207022
Active Contributor
0 Kudos

Hi,

Check your requirements for the production order components may be falling out the factory calendar validity period.

Also check the OSS note 846863,  204127.

Regards

Ganesh M

SaniketK
Participant
0 Kudos

Hi Ganesh,

I have already tried with OSS note 846863,  204127. But they are not system shows "Note cannot be Implemented".

Regards,

Saniket

dejoy
Active Contributor
0 Kudos

Dear,

In which release you are?

Regards,

SaniketK
Participant
0 Kudos

Hi Dee Joy,

Client using ECC 5.0 release.

Please suggest any suitable OSS Note, We tried with OSS note 846863,  204127 but these are not supported.

Regards,

Saniket

former_member211676
Contributor
0 Kudos

Hi Saniket

Could you check by what format you are entered date while creating process order and also go to

Menu bar system--> user profile --> Own data.

In the defualt values check your date format and enter the date in same.

Regards

Kesava

SaniketK
Participant
0 Kudos

Hi Ganesh,

Thanks for your quick reply, i have checked as you mentioned in T-code SCAL and extended the factory calender period. But still I am facing the at the time of order release. Also client never maintained Capacities for the resources.

@ Dee Joy,

Joy is there any other way to solve this error other than implement the note.

Regards,

Saniket

Former Member
0 Kudos

Are you using planning calender in any of assigned components. If yes, please check the date range of planning calendar.

former_member209265
Active Contributor
0 Kudos

Hi,

Which format the date you have given? Try to select the date from F4 help.

Check the calender also. If possible provide the screen shot.

Regards,

Krish.

SaniketK
Participant
0 Kudos

Hi Krish,

Date format is correct, see the screen shot.

Regards,

Saniket

dejoy
Active Contributor
0 Kudos

Hello saniket,

This is related to MRP. Have you checked the OSS  549193 - FAQ: Error messages in the material requirements planning

? Please check question 2 in this and revert back.

Regards,