Not able to create Service PR using CJ20N

Hi All,

I am creating service PR using T.Code CJ20N & i am getting dump " Update was Terminated" & not able to generate Purchase Requisition for services.

This error is coming for a single WBS Element only rest are working fine.

I am able to create new Activity under the same network then system is allowing me to create the Service PR.

Please help me to get the solution for the same.

For Reference I am attaching the ST22 Dump Screen Shot.

Regards,

Neha Srivastava

Capture1.PNG (26.8 kB)
Capture2.PNG (30.0 kB)
Capture3.PNG (27.2 kB)
Capture4.PNG (37.1 kB)
Capture5.PNG (26.5 kB)
Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

7 Answers

  • Posted on Dec 30, 2013 at 06:26 AM

    Hi

    It seems there is some user-exits or some validations are there in the execution of std. program.

    Kindly check with the ABAPer on it and find out the root cause.

    You may also debug the same to find the cause.

    Regards

    Saurabh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 30, 2013 at 07:15 AM

    Hello Raj,

    Few days back also we faced similar type of issue.

    When we checked it was observed root cause of the PR missing is whenever the activity is fully confirmed in CN25 or CN27 transaction, PR number was going missing from the activity

    You may check following SAP notes

    887342 - ME808/ME683 - system error: error updating table EBAN

    1588692 - SAPSQL_ARRAY_INSERT_DUPREC after save of material component


    If this does not resolve your issue, raise OSS message to SAP.


    Regards

    Tushar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 02, 2014 at 05:49 AM

    Hi All,

    Thanks for your prompt response. But I am getting dump while attaching Service activity element to the activity. If I am attaching material component then system is generating the PR.

    Kindly help me.

    Thanks & regards,

    Neha Srivastava

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi,

      How many Activities /Activity elements you have used under that assined network?

      Is it in a large number? if yes, then its a performance issue. You may check a SAP note on it.

      You should try to debug the program to analyze the root cause. As I stated earlier some validation/ckecks are cause the error.

      Regards

  • author's profile photo Former Member
    Former Member
    Posted on Jan 02, 2014 at 12:17 PM

    Hi,

    Please check while you are doing this activity , whether system is trying to post some CO (document) - as in your screen shot it looks like ( it is using OBJNR for COEP table).

    It is just like when you add material component to network while creating New project system does not save Network no.

    So just try to check which object no it is using.

    I think it is updating some document - (LKAUPU01-K_DOCUMENT_UPDATE)

    Regards,

    Sandeep V


    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 03, 2014 at 07:28 AM

    Hi All,

    Thanks for your response. I am attaching only one service activity element and that network is assigned with only one service activity element and multiple material component. I am unable to find out the root cause.

    Please help.

    Regards,

    Neha Srivastava

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 03, 2014 at 09:19 AM

    Hi,

    Is this project in which you are trying to assign service activity element, a new project being created ?

    AND

    has it got any validations being checked,in the background ?

    AND

    Has this issue been observed in other projects in your system ?

    Regards,

    M.Amarendra

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 03, 2014 at 09:30 AM

    Hi Sandeep & Amarendra,

    I am attaching the service activity element in the existing project & this project is already having multiple services & material component.

    This dump is coming in a single network.Other networks are working fine.

    This error has been observed in a single project.

    Regrads,

    Neha

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.