It seems ME2O not able to monitor Schedule Agreement's subcontract item.

214 Views


Hello all,

It is my Schedule Agreement question again, what a new year gift..

Anyway, my question is ...

When a standard subcontracting purchasing order created via ME21N, ME2O is able to show and to track the components which need to provide to the subcontractor.

However, when a Scheduling Agreement (SA) created via ME31L, the ME2O is NOT able to show the component require to provide to the vendor (system show green color message at the button of the screen saying "No Selection Possible) even I have run the following steps for the SA.

* ME35L (release it),

* ME9L (print the SA),

* Delivery Scheduling created via MRP

* ME84 (create SA release)

* ME9E (print the SA release)

I went to MBLB to see if there is component already appear under the subonctractor, the screen output is blank.

All my master data (from MRP view in material master, PIR with subcon, source list <except some question i have on a forum i just post) are maintained perfectly.

Is this some kind of standad SAP of ME2O not applicable to SA's subcontract scenario.

Appreciate your enlightment.

Regards,

Daniel Tuff