Goods receipt end date cannot be before material staging

Former Member
0 Kudos

Dear Gurus,

Can you please shed lights if this availability check error  "V2, 162, Goods receipt end date cannot be before material staging"  is an valid error & if yes under what business context this error should be encountered ? BR

Accepted Solutions (1)

Accepted Solutions (1)

MANIS
Active Contributor
0 Kudos

Hi MD

As far as my knowledge says practically that scenario is not possible  where Material stg date > GR End date)

please check the below mentioned link about backward and forward schedulin

http://help.sap.com/saphelp_erp60_sp/helpdata/en/da/b55941ee23021de10000000a155106/content.htmg

Please let  me know if you need any further information.

Wish you a happy new year 2014

Cheers

Manish

Answers (1)

Answers (1)

MANIS
Active Contributor
0 Kudos

Hi Md

As per the code this erro comes when your

Material Staging / Availabilty date > Goods Receipt end date

or

( Material staging / Availablity date = Goods Receipt end date and

Material staging time > Goods Receipt end time)

you will find all this detail in the Purchage order / Delivery schedule tab

Hope this will help

Former Member
0 Kudos

Hello Manish,

Thank you for lending your helping hand.

Is this (Mat Stg Date > GR EndDate) a valid / realistic business situation ? If yes how to arrive to this situation?

But How does that situation occur , in other words what order of influencing factors viz. Requested Deliv Date, Shipping Point & Route parameters resulting in the Mat Stg Date > GR EndDate ?

Is not system kicking-off the backward then forward scheduling to avert such situation ( Mat Stg Date > GR EndDate ) & offer a realistic Delivery Schedule Line dates perhaps beyond the ECC planning horizon & APO planning calendar ?

Hope this is self-explanatory, comprehensive & sufficiently detailed..