Goods receipt end date cannot be before material staging

Dear Gurus,

Can you please shed lights if this availability check error "V2, 162, Goods receipt end date cannot be before material staging" is an valid error & if yes under what business context this error should be encountered ? BR

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    Posted on Jan 01, 2014 at 12:49 PM

    Hi MD

    As far as my knowledge says practically that scenario is not possible where Material stg date > GR End date)

    please check the below mentioned link about backward and forward schedulin

    http://help.sap.com/saphelp_erp60_sp/helpdata/en/da/b55941ee23021de10000000a155106/content.htmg

    Please let me know if you need any further information.

    Wish you a happy new year 2014

    Cheers

    Manish

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 29, 2013 at 09:21 AM

    Hi Md

    As per the code this erro comes when your

    Material Staging / Availabilty date > Goods Receipt end date

    or

    ( Material staging / Availablity date = Goods Receipt end date and

    Material staging time > Goods Receipt end time)

    you will find all this detail in the Purchage order / Delivery schedule tab

    Hope this will help


    2.JPG (49.9 kB)
    1.jpg (29.3 kB)
    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello Manish,

      Thank you for lending your helping hand.

      Is this (Mat Stg Date > GR EndDate) a valid / realistic business situation ? If yes how to arrive to this situation?

      But How does that situation occur , in other words what order of influencing factors viz. Requested Deliv Date, Shipping Point & Route parameters resulting in the Mat Stg Date > GR EndDate ?

      Is not system kicking-off the backward then forward scheduling to avert such situation ( Mat Stg Date > GR EndDate ) & offer a realistic Delivery Schedule Line dates perhaps beyond the ECC planning horizon & APO planning calendar ?

      Hope this is self-explanatory, comprehensive & sufficiently detailed..

      BR

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.