Auto generated Service PR with acc. assignment P

soubhagya_rout
Participant
0 Kudos

Hi Guys,

Can you please help on this?

While generating PR from Network activities:

In case of material, PR generated with account assignment Q and in the acc. assignment tab WBS element field captured the WBS element from activities.

where as in case of Service, PR generated with acc. assignment P and item category D but here the problem is, the WBS element field is blank and only network and activity fields are captured.

Is there anything I am missing in config or it is the standard SAP behavior? If it is the standard SAP behavior, then kindly let me know how to capture WBS element instead of Network and activity.

WIth Regards,

Soubhagya Rout

Accepted Solutions (0)

Answers (3)

Answers (3)

chaitanya463
Explorer

It is standard SAP behavior. These settings are made in configuration under OPTT. So, we go to tcode ‘OPTT’ – To configure Account assignment categories for order. If you raise PR from network activity then it will pick 'N' as configured under account assign. General in OPTT (its 'P' in your case). And if you trigger PR on WBS then it will pick 'Q' as configured in OPTT under Account assignment cat Projects.


With OPTT config. You can replace 'P' with 'N' and that will ultimately charge to the account assigned WBS of the respective network. There is no point of having a WBS element field in place instead of P or N when the purpose of charging WBS can be filled with 'N' itself.
Even if you insist then in OME9 you can make the 'Project' field as Mandatory entry but that will be in display only.

As per the other's comments ,you may go with a Z-document type and Z-account assignment category configured under MM and make the WBS element field as mandatory with the above given selection and assign the same in OPTT, OME9 also

former_member195427
Active Contributor
0 Kudos

Hello Soubhagaya,

It is std. SAP behavior. These settings are made in configuration under OPTT. If you raise PR from network activity then it will pick 'N' as configured under account assign. general in OPTT (its 'P' in your case) . And if you trigger PR on WBS then it will pick 'Q' as configured in OPTT under Account assignment cat Projects.

Regards

Saurabh

soubhagya_rout
Participant
0 Kudos

Hi Saurabh,

Well I have already configured that.

My question is, how to capture WBS element instead of Network and activities in case of auto generated service PR from network activity with account assignment P and item category D?

With Regards,

Soubhagya rout

former_member195427
Active Contributor
0 Kudos

Hi Saubhagya,

With OPTT config. you can replace 'P' with 'N' and that will ultimately charge to the account assigned WBS of the respective network. There is no point of having a WBS element field in place instead of P or N when the purpose of charging WBS can be filled with 'N' itself.


Even if you insist then in OME9 you can make the 'Project' field as Mandatory entry but that will be in display only.

OR

You may go with a Z-document type and Z-account assignment category configured under MM and make the WBS element field as madatory with the above given selection and assign the same in OPTT, OME9 also.

Regards

Saurabh

soubhagya_rout
Participant
0 Kudos

Hi Guys,

Is there any way out?

With Regards,

Soubhagya

sanjeevc
Active Contributor
0 Kudos

Hi,

As far as i know Two Purchase Req. doc types can not be manage in sap PS standard.

So go through "Z development" with ABAP team for this.

Rest wait for expert comments.

Regards,
Sanjeev

former_member195427
Active Contributor
0 Kudos

Hi Sobhagya,

Not sure of any other standard. way.

I would sugest you to go with development on it.

With Regards

Saurabh

0 Kudos

Hi Saurabh,

could you please suggest how can we handle this using development ?

I tried looking for BADI, Exit but did not find any.

Thanks,

Former Member
0 Kudos

Hi,

If you create a service PR through PS Module, then system generate the PR at Network and activity level.

If you want Service PR at WBS level, so you create a service PR manually though MM module(T-Code ME51n).

Regards

GAurav