Is there any option to choose PRT while doing production posting / confirmation?

The scenario is that we are manufacturing a part by more than one PRT (Mould / Die). If we attached more than one PRT as a equipment in the routing for a particular operation, life time for the same will be calculated for all the attached PRT's.

So i need to choose the correct PRT while doing confirmation. Please clarify my doubt at the earliest.

Thanks & Regards,

Nellaiappan N.P.

Accepted Solutions (0)

Answers (3)

Answers (3)

sundaresan_velayudam
Active Contributor
0 Kudos

Is there any option to choose PRT while doing production posting / confirmation?

Not possible.

Work around

For one operation maintain One PRT and set the control key confirmation Not Mandatory.

While confirming Choose the correct operation and confirm the same, there by system will update the counter for the Particular PRT

Anupam1143
Active Contributor
0 Kudos

Hi,

You can define additional paramter in SVK which is not relevant for costing etc for recording the PRT information while doing confirmation and report can be generated from AFRU.

Check and revert.

Regards,

Anupam Sharma

Former Member
0 Kudos

Hi,

Please clarify what is meant by SVK parameter

former_member209265
Active Contributor
0 Kudos

Hi,

As per my understanding confirmation will happen on phase/operation level. There is no field to confirm in PRT level. One easy way is to add one operation for one PRT. But not sure how much convenient for your scenario.