on 12-24-2013 12:37 PM
Hi Friends,
What is commitment cost against any project. In which tcode I can see commitement cost for specific project.
Can you please help me in understanding how it is calculated.
Kiran CG
Hi,
The commitment cost is nothing but the PR/POs against the project which are not yet invoiced. You can check in tcode CJI5 in Val/CO Area Crcy.
Or you can check in tcode S_ALR_87013558 by:
Enter Project & execute-> select commitment value ->go to in menu bar -> then click on line items
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Kiran,
Please search the forum... There are lots of threads you will find on commitment.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kiran,
Yes, for open POs for which no GR & IR done, you can check the same in CJI5 report by clicking on 'Open Items only'
Check following SAP note for more info on commitments
152571 - Composite SAP note: Missing or incorrect commitments
Regards
Tushar
Hi Kiran
commitment cost is equivalent to all cost that will be directly attributed to your project through PR and PO's and needs to be funded. You can monitor it through CJI5 transaction.
Hope it helps
Pan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.