While executing the WBS settlement into G/L account which is a cost element system is giving the error message: "Account XXXX requires an assignment to a CO object".

We have also maintained the Cost Center in details tab of settlement rule.

Requirement: We do not want to assign default account assignment in KA02 or OKB9.

Kindly suggest how to assign the account assignment in settlement rule only .

Thanks and Regards,
Sarvendra Negi

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    Posted on Dec 22, 2013 at 06:17 AM

    Hi Sarvendra,

    Implement note 483340. The system will take the cost center you entered in the settlement rule as cost object while settling to GL. In standard the cost object in settlement rule is not considered.

    Regards,

    Sangram

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 22, 2013 at 05:30 AM

    Check whether you can maintain cost center in WBS element.

    Thanks

    SKKS

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.