How to assign Pm sub assembly in pm main assembly

I was trying to assign pm sub assemby into pm assemby by system giving error message pm assemby not maintained in plant .As pm assemby we are creating with out assingning to any plant.

Advance thanks for solution

REgards

Anand

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Dec 26, 2013 at 06:51 AM

    Hi Anand,

    1.Please create Maintenance Assemblies with the Material Type as IBAU by using the transaction code MM01.

    2.Create Equipment BOM by using the transaction code IB01 and give the Item Category as "I" (PM structure element) and enter the Maintenance Assembly number which was created in the earlier step.

    As you said in your thread, for IBAU materials there is no plant specific data will be maintained and you can use it for any plant.

    Please note that PM assemblies you can not assign in Materail BOM in CS01 transaction code.PM assemblies you can assign only in Equipment BOM (IB01).

    Best Regards

    Kalyan

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 21, 2013 at 11:39 AM

    Assemblies are the type of materials. Unless, you extend that to some plant, you can't assign that to main assembly in BoM.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 26, 2013 at 12:39 PM

    elaborating the KD's words further, extend the assembly material no. (IBAU) with MM01, choose required view on selection screen (image_a), mention required plant (image_b), edit any value if required and save. same procedure is followed to extend it for Storage locations or Valuation types.


    mm01_c.PNG (36.0 kB)
    mm01_b.PNG (17.7 kB)
    mm01_a.PNG (31.2 kB)
    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 26, 2013 at 06:31 AM

    hi ,

    Please suggest how to extend pm assembly to plant

    Regards

    anand

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Go to MM01. Mention the Material Code. Select the views which are related to Plant viz., MRP, Plant Data, Stock views.

      I hope, you are not MM consultant. If you have anyone, check with them on extending materials to plant.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.