on 12-21-2013 11:02 AM
I was trying to assign pm sub assemby into pm assemby by system giving error message pm assemby not maintained in plant .As pm assemby we are creating with out assingning to any plant.
Advance thanks for solution
REgards
Anand
Hi Anand,
1.Please create Maintenance Assemblies with the Material Type as IBAU by using the transaction code MM01.
2.Create Equipment BOM by using the transaction code IB01 and give the Item Category as "I" (PM structure element) and enter the Maintenance Assembly number which was created in the earlier step.
As you said in your thread, for IBAU materials there is no plant specific data will be maintained and you can use it for any plant.
Please note that PM assemblies you can not assign in Materail BOM in CS01 transaction code.PM assemblies you can assign only in Equipment BOM (IB01).
Best Regards
Kalyan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi ,
Please suggest how to extend pm assembly to plant
Regards
anand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Assemblies are the type of materials. Unless, you extend that to some plant, you can't assign that to main assembly in BoM.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.