Capacity planning

Jan 16, 2017 at 07:23 PM

24

avatar image

Hi Sapients,

I came across the scenario where the capacity load is not being reduced even though planned order has been partially converted to Process order.

For Example , I been have created PIR of 100 MT in MD61. After running MRP, planned order has been generated for 100 MT. But as per the capacity formula in the Resource , it can produce 90 MT in 10 hrs. Now as per the capacity formula ,in planned order it is showing over load. But when converting the planned order partially into process order of 50 MT, capacity load in planned order is not being changed. But in discrete manufacturing in the capacity , can give the formula as proportional to service, but in resource I had n't found. In this case how to do? Please guide on tis.