hi

We have not implemented batch management during implementation. But now we wanted to maintain batch for saleable products (FERT - Finished product). Please let us tell the procedure to implement batch managment at this level. We already have purchase orders, sale orders and production orders etc.

regards

padma

Accepted Solutions (1)

Accepted Solutions (1)

former_member182609
Active Contributor
0 Kudos

Addition to above You can do Batch Management activation .Before activating Batch Management you need to clear all old stock and clear open documents .So that system will allow you to activate batch.

We did this activity before.The challenge is clearing the stock and documents.

Answers (3)

Answers (3)

srinu_s1
Active Contributor
0 Kudos

Hi Padma,

As already indicated by other member, before activating any materials, you need clear all the open orders and open PO if any.For detailed explanation please follow the below document, which is very helpful.

I hope this will help to resolve your issue.

thanks,

Srinu.

rahul_vishwakarma2
Contributor
0 Kudos

This message was moderated.

siva_vasireddy2
Active Contributor
0 Kudos

Hi,

Batch Management cannot be Implemented at this stages as you already have corresponding Documents