Former Member
0 Kudos


Some maintenance Tasks are relevant for the integrated activity plan. The integrated activity plan is a Long term plan which shall include the most relevant activities for the Business across all departements (the integrated activity plan is managed outside sap in a Project Management Software).

How can workorders be flagged so that the planner can identify them as relevant for the integrated activity plan. Planner will filter IAP WO to update the integrated activity plan.

I was looking into revisions (IAP Revision) but work orders - as far as I know- can only be part of one Revision. One way might be to have a custom field on work orders. Workorder types and activity types we use for maintenace Task types (i.e. preventive, corrective, ....) so I would prefer not to use them for IAP relevant work orders.

Any ideas to solve the Problem?

Accepted Solutions (1)

Accepted Solutions (1)

peter_atkin
Active Contributor
0 Kudos

Is this at order header, and/or operation level?

In the mean time, have a look at the Maintenance Activity Type or System Condition fields.

PeteA

Former Member
0 Kudos

it is on order Header only not on operations Level. Order activity type I prefer not to use, i will look into System condition field.

thanks Rod

peter_atkin
Active Contributor
0 Kudos

Rod,

One thing to consider with the System Condition field is that it is a global table i.e. it cannot have values by plant or order type.

It is also limited to 1 character, so effectively 36 combinations (A-Z, 0-9, ignoring control characters)

This may require agreement from your global group.

Just to clarify; you may need an order to be assigned to multiple groupings?

PeteA