HOW TO ACTIVATE ENTERPRISE CALENDAR?

Former Member
0 Kudos

Hi everyone, i allready create my enterprise calendar but i dont know  the process to activate it.

thanks by advance for your answers!

Accepted Solutions (1)

Accepted Solutions (1)

kaushalya
Active Participant
0 Kudos

Hi Moise,

If you have created your SAP calendar in DEV server, you have to transport it to Production server.

You can set-up the 2014 calendar by assigning the holidays to your Factory calendar.

Hope this guide >> scn.sap.com/community/erp/blog/2012/12/31/creating-factoryholiday-calendar << will help you!

Former Member
0 Kudos

Hi Kaushalya,

I really appreciate your link,thank you! it is just the answer i was waiting for.

Regards,

kaushalya
Active Participant
0 Kudos

You're welcome! I'm glad it was useful!

Former Member
0 Kudos

This message was moderated.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Moise,

If you are talking about Holiday Calendar (SCAL / OY05) as said by Siddharth above, there won't be any activations needed.Below steps my explain you the process.

  1. Creating Public Holidays
  2. Creating Holiday Calendar
  3. Assigning Public Holidays to Holiday Calendar
  4. Transport Holiday calendars
  5. Assigning Holiday Calendars to Time management groupings
  6. Generating Work schedules according to groupings