Customising of lot sizing and work centres

Anyone to assIstanbul with the menu path of defining cost centers for work centers and defining lot sizing for finishing product . Alternatively if I can get the transcational codes I will appreciate more

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jan 17, 2017 at 09:58 PM

    Lot size procedures are stored in customizing (you should take a look in SPRO in MRP segment).

    Cost Centers are defined for FI-CO specialist and it maintain via KS03, additional to this you may required to create activity types related with the Standard Value Key that your are using in such work center. Some more activities/detailed may be required for the accounting/cost side, so please validate with this specialist.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 18, 2017 at 11:15 PM

    thank you very much that was very helpful

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 19, 2017 at 11:55 AM

    Hi Vincent,

    Hope this helps

    Transaction for defining cost centers for work centers: CR02 Production -> Master Data -> Work Centers -> Work Center -> Create

    Transaction for defining lot sizing for finishing product: MM02 Materials Management -> Material Master data -> Material -> Change -> Change material Transaction for defining lot sizing for finishing product mass: MM17

    Thanks

    Deepa