on 12-17-2013 12:07 PM
Hi all,
I have this material planning in the network activity in CJ20N which is 768,977.00 USD.
However, when I open in CN41 and look for Project cost sch 000 for this network activity, the amount is 2,471,687.00 USD.
Could you please advise how can I check on the detail line items that sum up the amount of 2,471,687.00 USD?
I do not understand why there is such a huge different of amount showed between CJ20N and CN41?
Could anyone advise? What can be the possible root cause of this and how to check?
Thanks.
Jessie
Hi,
Please double click on line item to get the details of Line Item in CN41 report and get the details where actually the plan cost has been updated in CJ20N
Thanks
Shashank Gaur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.