SAP B1 V8.82PL12 Remove Main Budget

Former Member
0 Kudos

Hi,

My clients use SAP business one V8.82 PL 12 system.  The main 2013 budget date is from Jan, 2013 to Dec, 2013. The Second company 2014 budget set as fiscal year from April, 2014 to March, 2015. Actual it should be fiscal year for the posting period. I went back  to fix the main budget. The system asked me to first remove the main budget then I can reenter the fiscal year 3013 budget. I cannot remove the main budget. When I did it, the system message showed nothing. Can everyone help me solve the main budget calendar year problem?

Thank you,

Rong Zhang

Accepted Solutions (1)

Accepted Solutions (1)

kothandaraman_nagarajan
Active Contributor
0 Kudos

Hi,

System will not allow to remove main budget. For more details, please refer how to guide for budget,

http://www.b1implement.com/SAPImplementDemo/HowTo_Mg_Budgets_88.pdf

Thanks & Regards,

Nagarajan

Former Member
0 Kudos

Hi Nagarajan,

Thank you for you reply. Finally, I asked SAP for help. They helped me remove the main budget using the SQL script. They said We can backup the before and after production database.

Regards,

Rong

kothandaraman_nagarajan
Active Contributor
0 Kudos

Hi,

Thanks for feedback.

Regards,

Nagarajan