Hellow all,
my scenario:
1. WBS determines dates
2. Method: free scheduling
3. 2 levels hierarchy of WBS's
4. Basic dates are maintained at WBS top level (only)
5. One network header assigned to WBS top level
6. Activities network are assigned to WBS's level 2
now for the question:
When I schedule the project, I expected that behavior system will agregate activity schedule dates to WBS top level, actually, only WBS's level 2 (that the activities are assigned to) agregates the scheduling dates from their relevant activities. In the scheduling dates of top WBS it seems that the result are the same as basic dates.
can anyone please explain me the rationale that stand behind this behavior? is it possible to configure the system so that WBS top level will agregate in schedulind dates results, all activities that assigned to WBS's level 2?
Graphic explanation at the attached file.
thank in advance,
Best regards,
Nir