Hi Gurus,
My situation is as follows:
Plant A: only trading goods.
Materials are supplied from another plant B (same company code) through stock transport orders. Then plant B is the supplying plant of plant A, and I made the stock transport configuration to allow this.
Plant A:
MRP run on 16/12: stock quantity is below the safety stock -> new requirement : Automatic PR creation with plant B as supplying plant.
MD04: receipt date is D date + delivery date
In my example: 16/12 + 1 = 17/12
Plant B:
A PRqRel is visible in MD04 accordingly to the PR.
No stock available in plant B to cover this PR.
MRP run on plant B on 16/12: an automatic PR is created (which will be converted to a standard PO).
MD04: receipt date is D date + delivery date
In my example: 16/12 + 3 = 19/12
My question:
I would assume to receive a new date for this material in plant A because my material will only be available on 20/12 (19/12+1).
I run MRP on plant A again, and nothing change: still have the receipt date : 17/12.
I would have expected to get 20/12 as rescheduling date or any information to inform plant A of this new date.
Is it possible? Did I miss something in my settings to support this?
Thanks a lot in advance.